Upgraded line between Angermuende and Szczecin
The upgraded line between Angermuende and the German-Polish border is of great significance for European rail transport. The section between Passow and the German-Polish border is 30 km long. This section will also be double-tracked, electrified throughout and the line speed increased from 120 km/h to 160 km/h.
The project will include modernization of five stations and the renewal of railroad installations. The entire line will be equipped with the European Train Control System (ETCS) – Level 2 to increase reliability and safety.
Project information
- The project is broken down into two planning approval sections
- Planning approval section 1 Angermuende–Passow (19 km)
 - Planning approval section 2 Passow–Tantow–D/PL border (30 km)
 
 - Renewal of 5 stations
- Passow station
 - Schoenow stop
 - Casekow station
 
- Petershagen stop
 - Tantow station
 
 - Equipping with ETCS Level 2
 - Construction during ongoing rail operations
 
Planning approval section 1:
- The goal is to increase speed to 160 km/h
- Renewal of permanent way
 - Renewal of overhead line
 - Renewal of underground cable installation
 - Adjustment of control-command and signaling
 
 - Renewal of 4 railroad overpasses
 - Replacement of an overpass with new structure
 - Construction of an electronic interlocking outdoor unit near Schoenermark
 - Construction of noise barriers in the area of Angermuende station
 
Planning approval section 2:
- The goal is continuous double-tracking and electrification as well as increasing speed to 160 km/h
- Renewal of permanent way
 - Construction of new overhead line
 - Renewal of underground cable installation
 - Adjustment of control-command and signaling
 
 - Replacement of 2 railroad overpass with new structures
 - Construction of noise barriers in the local area of Casekow, Petershagen and Tantow
 - Preparation of environmental impact assessment, environmental impact mitigation plan, Natura 2000 expert opinion and expert opinion on wildlife conservation
 




